Kolkata Environmental Improvement Project (KEIP) is a multi-agency endeavour to arrest environmental degradation and improve the quality of life in Kolkata. Its work is mainly in the outer areas of the city where the sewerage and drainage infrastructure is grossly inadequate and the drainage canals are choked by silt.

KEIP’s  objectives  are  to  reduce  pollution

by providing affordable access to basic urban services in slums, revamp and up grade the sewerage and drainage system, make solid waste management system efficient,restore the city's drainage canals , and improve outdoor recreation facilities in parks and water bodies. It also has a capacity building component to raise the standards of KMC’s delivery of municipal services.

 Untitled
 
Project Update
The Project has gained considerable speed in the last 12 months. Some long-standing canal bank dwellers’ resettlement issues have been resolved. Consequently, the canal rehabilitation strategy has been revised so that there is better synergy between the Project’s work on the sewerage and drainage network and canals.

Some of the major achievements are:
All the land required for resettlement is in KEIP's possession and the work is in progress.
A total of 2810 Families are already resettled against a total of 3365.
 Summary Status ** Quarterly Progress Report
 Financial status as on 31st March, 2011
 Expenditure incurred (including I&WD)

 Upto 2009-10 Fiscal

INR   1,080.13 crore

 In 2010-11 April-June'10 (Quarter I)

INR   44.86 crore

 In 2010-11 July-Sept'10 (Quarter II)

INR   85.39 crore

 In 2010-11 October-Dec'10 (Quarter III)

INR   37.64 crore

 In 2010-11 January-Mar'11 (Quarter IV)

INR   104.74 crore

 Total expenditure

INR 1,352.76 crore

 Financial status as on 31st March, 2011
 Expenditure incurred under 1813 IND

 Upto 2009-10 Fiscal

INR   828.86 crore

 In 2010-11 April-June'10 (Quarter I)

INR   33.98 crore

 In 2010-11 July-Sept'10 (Quarter II)

INR   52.38 crore

 In 2010-11 October-Dec'10 (Quarter III)

INR   22.07 crore

 In 2010-11 January-Mar'11 (Quarter IV)

INR   75.95 crore

 Total expenditure

INR 1,013.24 crore

 Financial status as on 31st March, 2011
 Expenditure incurred under 2293 IND

 Upto 2009-10 Fiscal

INR   251.27 crore

 In 2010-11 April-June'10 (Quarter I)

INR   10.88 crore

 In 2010-11 July-Sept'10 (Quarter II)

INR   33.01 crore

 In 2010-11 October-Dec'10 (Quarter III)

INR   15.57 crore

 In 2010-11 January-Mar'11 (Quarter IV)

INR   28.79 crore

 Total expenditure

INR 339.52 crore

 Procurement Status of Equipment/Work
 Under 1813-IND
 Work  Package  No.   Bid Description   Contract No.   Contract Value
INR MN
  Name of the
Agency/Contractor
  Remarks
CW01
Construction of Pumping Stations at Different Canal Outfalls (TP, Keorapukur & Manikhali)
KEIP/ICB/CW01/ 2005-06

520.00

Kirloskar Brothers Ltd
Contract terminated on 08.08.09
CW03
Construction of Bridges on Canals - Package I
KEIP/LCB/CW03/ (BRIDGE/01)/2003-04

61.54

Mackintosh Burn Ltd.
Completed
CW04
Construction of Bridges on Canals - Package II
KEIP/LCB/CW04/ 2005-06

105.58

East Coast Engineers Ltd
Completion in March, 2011
CW05
Civil Works for Canal Rehabilitation (TP Basin downstream) - Package I
KEIP/LCB/CW05/ 2005-06

67.04

Mackintosh Burn Ltd.
Completed
CW08
Civil Works for Canal Rehabilitation (TP Basin midstream) - Package 2
KEIP/LCB/CW08/2006-07

47.46

A. K. Engineers
Completion in March, 2011
CW10
Civil Works for Canal Rehabilitation Manikhali-(upstream)
KEIP/LCB/CW10/ 2005-06

84.99

Mackintosh Burn Ltd.
Completed
CW11
Civil Works for Canal Rehabilitation Manikhali downstream-Package 5
KEIP/LCB/CW11/ 2006-07

76.66

GPT-GVV Joint Venture
Contract fore closed
CW12 LOT1
Civil Works for Canal Rehabilitation (Keorapukur)Package6, Lot 1
KEIP/NCB/CW12A/ 2006-07

31.30

GPT-GVV Joint Venture
Completion in May, 2011
CW12 LOT2
Civil Works for Canal Rehabilitation (Churial Extension) Package 6, Lot 2
KEIP/NCB/CW12B/ 2006-07

76.49

Mackintosh Burn Ltd.
Completed
CW22
Construction of Canal Pumping station at Chowbhaga
CW22

232.76

Voltas Ltd.
Work in Progress. Expected date of completion 20.10.2012
CW23
Construction of Canal Pumping station at Keorapukur
CW23

251.51

Voltas Ltd.
Work in Progress. Expected date of completion 20.10.2012
CW24
Construction of Canal Pumping station at Manikhali
CW24

213.96

Voltas Ltd.
Work in Progress. Expected date of completion 20.10.2012
RS1A
Resettlement of 165 Canal Bank Dwellers -VAMBAY-KMDA Phase 1

12.97

KMDA
Completed
RS1B
Resettlement of 352 Canal Bank Dwellers -VAMBAY-KMDA Phase 2

29.78

KMDA
Completed
RS1C
Resettlement of 64 Canal Bank Dwellers -VAMBAY-KMDA Phase2

5.04

KMDA
Completed
RSA1- 3
Resettlement of canal bank dwellers at Nonadanga - VAMBAY KEIP Package 1 - Lot 1-3
KEIP/LCB/RSA1-3/2005-06

100.94

Mackintosh Burn Ltd.
Completed
RSA4- 5
Resettlement of canal bank dwellers at Nonadanga & Purba Putiyari - KEIP Package 1 - Lot 4-5
KEIP/LCB/RSA4/RSA5 2005-06

52.51

Mackintosh Burn Ltd.
Completed
RSB
Resettlement of TP Basin upstream dwellers at Kasba- KEIP
KEIP/LCB/RSB/ 2006-07

38.83

RSB Projects Ltd
Completed
RSC
Resettlement of Manikhali Canal Bank Dwellers at Sampa Mirza Nagar
KEIP/LCB/RSC/ 2006-07

49.87

BGM Consortium
Completed
RSD
Resettlement of 256 Churial Bank Dwellers at Kalagachia
KEIP/LCB/RSD/2007-08

58.99

A.K. Engineeing
Completed
RSF
Construction of low cost Housing for Resettlement of 832 TP Basin dwellers at Nonadanga
KEIP/LCB/RSF/2006-07

114.94

Mackintosh Burn Ltd
Completed
SD12
Lake Rehabilitation Work Package I
KEIP/LCB/SD12/ (WB/01)/2002-03

32.00

Gondwana Engineers Pvt Ltd.
Completed
SD13 Lot1
Lake Rehabilitation Work Package II Lot1
KEIP/NCB/SD13 lot 1/ 2006-07

26.00

Rany - Devson JV
Completed
SD13 Lot2
Lake Rehabilitation Work Package II Lot2
KEIP/NCB/SD13 lot 2/ 2006-07

34.57

A.K. Engineering. Pvt Ltd
Completed
SD14
Procurement of Suction Machines
KEIP/IS/SD14/ (SUC/03)/2002-03

3.32

Southern Powertech Equip.(P) Ltd. and Shriram Engg Const Co. Ltd. (JV)
Completed
SD15
Procurement of Jetting Machines
KEIP/IS/SD15/ (JET/04)/2002-03

3.75

Southern Powertech Equip.(P) Ltd. and Shriram Engg Const Co. Ltd. (JV)
Completed
SD17
Construction of Sewerage & Drainage Network (Ward 111)
KEIP/LCB/SD 17 / 2004-05

3.66

P.Chatterjee & Co
Completed
SD18
Construction of Sewerage & Drainage Network (Ward 106)
KEIP/LCB/SD 18 / 2004-05

3.99

Essem Enterprise
Completed
SD19
Construction of Sewerage & Drainage Network (Ward 120)
KEIP/LCB/SD 19 / 2004-05

3.24

Teekay Management
Completed
SD20
Construction of Sewerage & Drainage Network (Ward 129)
KEIP/LCB/SD 20 / 2004-05

3.94

Markaton
Completed
SD21
Construction of Sewerage & Drainage Network (Borough I Ward 6)
KEIP/LCB/SD 21 / 2004-05

4.42

S. G. Construction
Completed
SD22
Construction of Sewerage & Drainage Network (Borough XV Ward 133)
KEIP/LCB/SD 22 / 2004-05

4.00

P.S. Construction
Completed
SD23
Construction of new DWF Pumping Stations in Boroughs XII, XIII & XIV - Package 1
KEIP/ICB/SD 23 / 2006-07

240.30

Mackintosh Burn Ltd
Completion in May, 2011
SD24 R1
Upgradation of DWF Pumping Stations in Boroughs XI, XIII & XIV Lot 1 (12 nos)
KEIP/LCB/SD24R1/ 2006-07

63.40

Mackintosh Burn Ltd
Completion in May, 2011
SD24 R2
Upgradation of DWF Pumping Stations in Boroughs I, XV Lot 2 (5 nos.)
KEIP/LCB/SD24R2/ 2006-07

31.40

Mackintosh Burn Ltd
Completion in May, 2011
SD25
Augmentation of STP (South Suburban East)-civil & Equipment-package 1
KEIP/LCB/SD25/ 2006-07

139.00

Voltas Ltd
Completed
SD26
Construction of new DWF Pumping Stations in Borough I
KEIP/NCB/SD 26 / 2006-07

118.80

Ramky Infrastructure Ltd
Completion in May, 2011
SD29
Augmentation & Renovation of Bangur STP
KEIP/NCB/SD 29 / 2007-08

49.71

Voltas Ltd
Completion in May, 2011
SD35A
Construction of Miscellaneous Civil Works Lot 1
KEIP/NCB/SD35A/2010-11

262.60

Jain Infraprojects Ltd.
Completion in July, 2012
SD35B
Construction of Miscellaneous Civil works Lot 2
KEIP/NCB/SD35B/2010-11

52.13

Mackintosh Burn Ltd.
Completion in January, 2012
SD36
Construction of Pumping Station of combined flow (DWF & SWF) at Padirhati
KEIP/NCB/SD36/2010-11

115.51

Voltas Ltd.
Completion in June, 2012
SDA1
Construction of Sewerage & Drainage for Borough XI including House Connection - LOT1
KEIP/ICB/SDA1/ 2004-05

448.10

Tantia Construction Co Ltd in joint venture with BSBK Ltd.
Completed
SDA2
Construction of Sewerage & Drainage for Borough XIII including House Connection - LOT2
KEIP/ICB/SDA2/ 2004-05

495.83

Simplex Concrete Piles (India) Ltd
Completed
SDA3
Construction of Sewerage & Drainage for Borough XI including House Connection - LOT3
KEIP/ICB/SDA3/ 2004-05

783.46

Simplex Concrete Piles (India) Ltd
Completed
SDB1
Construction of Sewerage & Drainage for Borough XIV including House Connection - LOT1
KEIP/ICB/SDB1/ 2004-05

514.31

Engineers Projects (India) Ltd
Completed
SDB2
Construction of Sewerage & Drainage for Borough XIV including House Connection - LOT2
KEIP/ICB/SDB2/ 2004-05

447.52

Tantia Construction Co.Ltd
Completed
SDB3
Construction of Sewerage & Drainage for Borough XIV including House Connection - LOT3
KEIP/ICB/SDB3/ 2004-05

299.52

Ramky Infrastructure Ltd
Completd
SDC
Construction of Sewerage & Drainage network - Borough XII
KEIP/ICB/SDC/ 2005-06

1.00

IVRCL Infrastructure Ltd
Completion in May, 2011
SDD1
Construction of Sewerage & Drainage network - Borough I (LOT 1)
KEIP/ICB/SDD1/ 2005-06

560.04

Tantia Construction Co Ltd
Completion in June, 2011
SDD2
Construction of Sewerage & Drainage network - Borough I (LOT 2)
KEIP/ICB/SDD2/ 2005-06

552.29

East Coast Engineers Ltd
Contract terminated on 10th July, 2009
SDD3
Construction of S&D Works in Borough I by using Micro Tunneling (Pipe Jacking Technique)
KEIP/ICB/SDD3/2008-09

318.10

Krita-MRI-Ohin J.V.
Completion in May, 2011
SI01
Civil Works of Slum Improvement - Package I
KEIP/LCB/SI01/ (SLUM/01)/2002-03

5.09

A.K. Engineering. Pvt Ltd
Completed
SI02
Civil Works of Slum Improvement - Package II
KEIP/LCB/SI02/ (SLUM/02)/2003-04

25.00

Civtech
Completed
SI03
Civil Works of Slum Improvement - Package III
KEIP/LCB/SI03/ 2003-04

59.50

Civtech
Completed
SI04
Civil Works of Slum Improvement - Package IV
KEIP/LCB/SI04/ 2003-04

23.87

A.K. Engineering. Pvt Ltd
Completed
SI05
Civil Works of Slum Improvement - Package V
KEIP/LCB/SI05/ 2003-04

35.04

Tantia Construction Company Limited
Completed
SI06
Civil Works of Slum Improvement - Package VI
KEIP/LCB/SI06/ 2003-04

21.56

Tantia Construction Company Limited
Completed
SI07
Civil Works of Slum Improvement - Package VII
KEIP/LCB/SI07/ 2003-04

52.20

Tantia Construction Company Limited
Completed
SI08
Civil Works of Slum Improvement - Package VIII
KEIP/LCB/SI08/ 2003-04

29.12

M/s. A.K. Engineers
Completed
SI10A
Civil Works of Slum Improvement - Package X Lot1
KEIP/LCB/SI10A/ 2005-06

20.27

SG Construction
Completed
SI10B
Civil Works of Slum Improvement - Package X LOT 2
KEIP/LCB/SI0B/ 2005-06

34.12

Progressive Construction
Completed
SI10C
Civil Works of Slum Improvement - Package X LOT 3
KEIP/LCB/SI10C/ 2005-06

27.95

Pre-stress
Completed
SI11
Civil Works of Slum Improvement - Package XI
KEIP/LCB/SI11/ 2005-06

40.24

RSB Projects Ltd
Completed
SI15
Transitional resettlement at Nonadanga for 460 families.
KEIP/LCB/SI15/ 2005-06

3.85

Eastern Stars Turnkey Engineers & Builders
Completed
SI15A
Basic Infrastructure facilities for transient resettlement works of canal bank dwellers at Nonadanga - Supply and installation of Solar Street lights
KEIP/LCB/SI15A/ 2005-06

0.45

Surya Bandhan
Completed
SI9A
Civil Works of Slum Improvement - Package IX Lot1
KEIP/LCB/SI09/ 2005-06

40.29

Spacetech Projects & Systems Pvt. Ltd
Completed
SI9B
Civil Works of Slum Improvement - Package IX Lot2
KEIP/LCB/SI09/ 2005-06

26.97

M/s. A.K. Engineers
Completed
SI9C
Civil Works of Slum Improvement - Package IX Lot3
KEIP/LCB/SI09/ 2005-06

30.91

Manoharlal Gupta & Co. Pvt. Ltd
Completed
SW07
Procurement of Mechnical Sweepers
KEIP/IS/SW07/ (MS/01)/2002-03

14.44

Brock Kerhtechnik GmbH
Completed
SW08
Procurement of Bull Dozer I
KEIP/IS/SW08/ (BDZ/01)/2002-03

8.08

BEML
Completed
SW09
Procurement of Bull Dozer II
KEIP/IS/SW09/ (BDZ/02)/2002-03

8.08

BEML
Completed
SWA1
Procurement of Vehicles - Package A Lot 2
KEIP/ICB/SWA1/ 2004-05

89.47

Ashok Leyland Limited
Completed
SWA2
Procurement of Vehicles - Package A Lot 2
KEIP/ICB/SWA2/ 2004-05

4.41

JCB India Limited
Completed
SWB1
Procurement of Vehicles - Package 2 LOT - 1
KEIP/ICB/SWB1/ 2004-05

13.53

Bharat Earth Movers Ltd
Completed
SWB2
Procurement of Vehicles - Package 2 LOT 2
KEIP/ICB/SWB2/ 2004-05

6.89

Bharat Earth Movers Ltd
Completed
SWB3
Procurement of Vehicles - Package 2 LOT 3
KEIP/ICB/SWB3/ 2004-05

37.81

Brock Kerhtechnik GmbH
Completed
SWB4
Procurement of Vehicles - Package 2 LOT 4
KEIP/ICB/SWB4/ 2004-05

46.50

Brock Kerhtechnik GmbH
Completed
SWB5
Procurement of 3 nos. Medium Mechanical Sweepers
KEIP/ICB/SWB5/2007-08

27.06

Brock Kerhtechnik GmbH
Completed
TOTAL 1813-IND
 
8,581.77
   
TOP
 Under 2293-IND
 Work  Package  No.   Bid Description   Contract No.   Contract Value
INR MN
  Name of the
Agency/Contractor
  Remarks
CW 09
Civil Works for Canal Rehabilitation (TP Basin upstream) - Package 3
KEIP/NCB/CW09/2005-06

115.75

GPT-GVV JV
Completion in May, 2011
CW 13
Civil Works for Canal Rehabilitation Suti Churial main canal system - Package 7
KEIP/NCB/CW13/2006-07

103.36

Mackintosh Burn Ltd
Completion in May, 2011
CW 14
Civil Works for Canal Rehabilitation Churial main canal system Package 8.
KEIP/NCB/CW14/2006-07

125.01

Dredging and Desiltation Pvt. Ltd.
Completion in Nov, 2010. Work held up due to local problem
CW 15
Civil Works for Canal Rehabilitation Churial diversion canal system Package 9.
KEIP/NCB/CW15/2006-07

136.39

Mackintosh Burn Ltd.
Completed
CW 19R2
Creation of Green Belts along TP, Monikhali and Churial Canals and in South Suburban East STP at Keorapukur
KEIP/NCB/CW 19R2/2007-08

12.84

Biswas Engineering
Completed
CW 25
Rehabilitation of EKW canals for improvement of Sewage Distribution System (South)
KEIP/NCB/CW25/2010-11

98.09

Mackintosh Burn Ltd.
Completion in February, 2012
CW12CR1
Civil Works for Canal Rehabilitation for Keorapukur Canal
KEIP/NCB/CW12CR1/2008-09

139.46

Macintosh Burn Ltd
Completion in April, 2012
CW12CR2
Civil Works for Canal Rehabilitation for Keorapukur Canal
KEIP/NCB/CW12CR2/2008-09

85.33

A.K.Engineers
Completion in March, 2012
CW20R1
Rehabilitation of EKW Canals for Improvement of Sewage Distribution System (North)
CW20R1

48.06

Macintosh Burn Ltd
Completion in May, 2011
CW20R2
Rehabilitation of EKW Canals for Improvement of Sewage Distribution System (North)
CW20R2

39.55

Macintosh Burn Ltd
Completion in May, 2011
CW20R3
Rehabilitation of EKW Canals for Improvement of Sewage Distribution System (North)
CW20R3

52.31

A.K.Engeneering
Completion in May, 2011
CW21 Lot 1
Rehabilitation of EKW canals for improvement of Sewage Distribution System (South)
CW21 Lot 1

73.70

Mackintosh Burn Ltd.
Work in Progress. Completion in December, 2011
CW21 Lot 2
Rehabilltation of EKW canals for improvement of Sewage Distribution System (South)
CW21 Lot 2

102.17

Mackintosh Burn Ltd
Work in Progress. Completion in December, 2011
SD 27
Construction of Sewerage & Drainage for Borough XIV including House Connection - LOT1
KEIP/ICB/SDB1/ 2004-05

119.18

WPIL
Delay damages imposed
SD 28
Augmentation of new DWF Pumping Station in Boroughs VII. (4 nos P.S.)
KEIP/NCB/SD28/2006-07

134.93

VOLTAS
Completion in May, 2011
SD 30
Augmentation of STP (Garden Reach)-civil -Equipment package 2
KEIP/NCB/SD30/2006-07

46.19

VOLTAS
Completion in May, 2011
SD 32
Construction of new DWF Pumping Stations in Boroughs XV- Package 3
KEIP/NCB/SD32/2006-07

96.69

WPIL
Completion in May, 2011
SD13CR
Improvement of Sarsuna & Padmapukur Lakes - Balance works
SD13CR

20.85

Kumar Associates
Completed
SDD4
Construction of S&D Network in Borough I including House Connection
SDD4

785.87

Simplex Infrastructure Ltd
Completion in July, 2012
SDE
Construction of Sewerage & Drainage network including house connection - Borough XV
KEIP/ICB/SDE/2006-07

850.35

Tantia Construction Ltd.
Completion in June, 2012
SDF Lot1
Construction of Sewerage & Drainage network, including house connection - Borough VII Lot 1
KEIP/ICB/SDF Lot 1/2006-07

360.11

Tantia Construction Ltd.
Completion in June, 2012
SDF Lot2
Construction of Sewerage & Drainage network, including house connection - Borough VII Lot 2
KEIP/ICB/SDF Lot 2/2006-07

495.59

Tantia Construction Ltd.
Completion in December, 2011
TOTAL 2293-IND

4,041.78

Grand Total

12,623.55

 Packages Tendered but yet to be awarded
 

No.

 

Description

 

Contract No.

 

Last date of Submission of bids/Remarks

 1813 IND
  SDD5   Construction of Underground pipe pushing work below Chitpur Railway Yard under Eastern Railway at Cossipore in Br. I   SDD5   Last date of bid submission is on 14.04.2011
 2293 IND
NIL
 Not yet tendered
 

No.

 

Description

 

Contract No.

 

Last date of Submission of bids/Remarks